November Water Tank Update

Hello Rimrockers,

There have been a series of challenges getting trucks up to the water tank site but we’re happy to report a major milestone in our progress. On November 20, eight, 8-yard concrete trucks and a large concrete pumper truck successfully made it to the water tank site. The slab base of the water tank was completed, and all went extremely well. Attached are some awesome pictures of pour day.

Unfortunately, all of the delays prevent the completion of the tank build this winter. The contractors will be back on site this spring when the weather warms up and dries out. All contractors have agreed to hold their 2025 prices, so we are well positioned to get this project operational.

We hope everyone has a safe and happy holiday season!

Board of Directors